Building Performance Standards Tracker: US Deadlines and Penalties 2026-27

hero background
Smart Buildings and IBMS

Building Performance Standards Tracker: US Deadlines and Penalties 2026-27

Back to all blogs

Short answer: Building performance standards are US city, county and state laws that make existing large buildings hit an energy or carbon limit, not just report it. We track eleven, each checked against its official text. The next filing dates bunch up between 1 May and 1 June 2027 (NYC, Cambridge, DC, Boston, Colorado, Maryland, Washington State, Denver, Montgomery County). Penalties run from $230 to $268 per excess tonne of CO2e, or per-day and per-square-foot fines.

Free Excel tool BPS Deadline Tracker comes free with this guide. Download now ↓

Applies to: US cities, counties and states, with a short comparison to the EU, UK and India.

Last reviewed: 13 Nov 2026. Every date and penalty below was checked against the official ordinance, regulation or programme page on this date. Refreshed quarterly.

This post covers who is covered where, the next deadline in each place, what the penalty text actually says, what changed in 2026, and the metering and data trail an owner needs to prove compliance.

  • NYC Local Law 97 fines a building "not more than" the excess tonnes times $268 (NYC Admin Code section 28-320.6, Local Law 97 of 2019).
  • Boston's BERDO sets an alternative compliance payment of $234 per tonne and a fine of $1,000 a day for buildings of 35,000 ft² (3,252 m²) or more that miss the standard (City of Boston Code 7-2.2).
  • Washington DC's first BEPS compliance cycle ends on 31 December 2026, with end-of-cycle reporting due 3 May 2027 (DOEE; D.C. Code 8-1772.21).
  • Maryland's first net direct emissions standard applies from 2030, with an alternative compliance fee of $230 per tonne for 2030 in 2020 dollars (COMAR 26.28.04.01).
  • Denver's Rules V6, adopted in August 2026, let owners who took the 2025 extension move targets to 2028 and 2032 (Energize Denver Rules section 4.7.E).

Asset Online Pvt Ltd (AOPL) supplies and integrates solutions in this area.

What are building performance standards?

A building performance standard (BPS) is a law that requires existing buildings above a size threshold to meet a measured performance level by a set date. The US EPA's ENERGY STAR programme defines them as policies that require commercial and multifamily buildings to meet certain performance levels, typically for energy use or greenhouse gas emissions.

Benchmarking only asks you to report. A BPS asks you to perform. Most US programmes build on an existing benchmarking law, so the same ENERGY STAR Portfolio Manager account that held your annual report now decides whether you pass. EPA says Portfolio Manager is the platform that all state and local benchmarking and disclosure policies run on.

Three metrics are used:

  • Energy use intensity (EUI): site energy per unit of floor area, in kBtu/ft² (US) or kWh/m². Washington State, Colorado, Denver, Montgomery County and Oregon use it.
  • Greenhouse gas intensity: kgCO2e or tCO2e per unit of floor area per year. NYC, Boston, Seattle and Maryland use it. Cambridge uses total emissions against a baseline.
  • ENERGY STAR score: a 1 to 100 rank against similar US buildings. Washington DC sets its standard by property type using this score.

Which US cities and states have building performance standards, and when are the deadlines?

The table lists the jurisdictions where we could open the law or programme page today. Thresholds are the main non-residential floor area in each rule. Smaller tiers (Washington State, Oregon) and multifamily rules differ, and the Excel download has the detail.

Jurisdiction Law Covered (non-res.) Metric Next date Penalty as written Official page
New York City Local Law 97 of 2019, Admin Code Art. 320 Over 25,000 ft² (2,323 m²) tCO2e per ft² per year 1 May 2027 report for 2026 emissions Up to excess tCO2e x $268 (28-320.6) nyc.gov
Boston BERDO City Code 7-2.2 20,000 ft² (1,858 m²); limits from 2025 at 35,000 ft² (3,252 m²) kgCO2e per ft² per year 15 May 2027 report $1,000/day (35,000 ft²+), $300/day smaller; ACP $234/t boston.gov
Cambridge MA BEUDO Municipal Code Ch. 8.67 25,000 ft² (2,323 m²); cuts from 2026 at 100,000 ft² (9,290 m²) GHG vs baseline 1 May 2027 report Warning, then up to $300/day; credit $234/t cambridgema.gov
Washington DC BEPS D.C. Code 8-1772.21 50,000 ft² (4,645 m²); 25,000 ft² from 2029 ENERGY STAR score 3 May 2027 end-of-cycle report ACP up to $10/ft², max $7.5m DOEE helpdesk
Washington State CBPS RCW 19.27A.210 Tier 1 over 50,000 ft² (4,645 m²) Site EUI vs target 1 Jun 2027 (90,001 to 220,000 ft²) Up to $5,000 + $1/ft²/yr (RCW); Commerce assesses $5,000 + $1.50/ft² commerce.wa.gov
Maryland BEPS Env. Art. 2-1602; COMAR 26.28 35,000 ft² (3,252 m²) Net direct emissions, kgCO2e/ft² 1 Jun 2027 benchmarking; standard from 2030 Fee $230/t for 2030 (2020 dollars) COMAR 26.28.03.02
Montgomery County MD County Code Ch. 18A Art. 6 Most buildings 25,000 ft² (2,323 m²) Site EUI 1 Jun 2027 benchmarking; interim year 2028 Class A violation: $500, repeat $750 montgomerycountymd.gov
Colorado BPS 5 CCR 1001-32 (Regulation 28) 50,000 ft² (4,645 m²) EUI, % EUI cut or GHG intensity 1 Jun 2027 report for 2026 Up to $2,000, then $5,000 per violation Regulation 28
Denver (Energize Denver) DRMC Ch. 10 Art. XIV; Rules V6 25,000 ft² (2,323 m²) Weather-normalised site EUI 1 Jun 2027 benchmarking; 2027 target year Up to $0.35, $0.23 or $0.15 per kBtu short denvergov.org
Seattle BEPS Seattle BEPS law, 2025 Director's Rule Over 20,000 ft² (1,858 m²) GHG intensity 1 Oct 2027 verification and GHG report (over 90,000 ft²) Not stated in the Jan 2026 guide seattle.gov
Oregon BPS HB 3409 (2023), ODOE rules Tier 1: 35,000 ft² (3,252 m²) Site EUI vs target 1 Jun 2028 (200,000 ft²+) No report: up to $5,000 + $1/ft²/yr ODOE FAQs
Timeline of next building performance standard dates: NYC and Cambridge 1 May 2027, Washington DC 3 May 2027, Boston 15 May 2027, Colorado, Maryland, Washington State, Denver and Montgomery County 1 June 2027, Seattle 1 Oct 2027, Oregon 1 June 2028; NYC, Boston, Colorado and Maryland step up in 2030
Next filing date and next performance year for 11 US jurisdictions. Sources: official ordinances, regulations and programme pages opened 13 Nov 2026. Chart: AOPL.

Two things stand out. First, nine of the eleven have something due between 1 May and 1 June 2027, so the 2026 calendar year you are in now is the data year that counts. Second, most programmes have a bigger step in 2030 (NYC, Boston, Maryland and Colorado), and retrofits take one to three years to show up in a full year of meter data.

What changed in 2026: pauses, delays and amendments

Several rules moved this year. This is what the official texts say today.

  • Maryland: No pause in the law. Chapter 844 of 2025 (HB 49) took effect on 1 October 2025 and orders the Department of the Environment to send a cost-benefit analysis of emissions-based, EUI-based and combined standards by 31 December 2026. In the 2026 session, the exemption bills for buildings with an occupancy permit before 1 June 2022 (HB 1217 and SB 479) and the repeal bill (HB 988) went no further than their committee hearings. The one 2026 law on the subject, Chapter 412 (HB 870, in force 1 October 2026), makes counties and towns notify the Department of permit applications for new buildings of 35,000 ft² or more. It does not change the standards. In COMAR 26.28.03.02 the EUI section (B) reads "Reserved", so only the emissions standard is in the current text.
  • Colorado: Regulation 28 was amended in September 2025 (effective 14 November 2025) and corrected on 17 June 2026. The amendment exempts agricultural buildings and moves the $100 annual fee to 1 November from 2026. The 2026 standard still applies to calendar years 2026 to 2029 (Part C, section I). We found no 2026 rule making it voluntary.
  • Denver: The city updated the ordinance in April 2026 and adopted Rules and Regulations V6 in August 2026. Owners who took the 2025 timeline extension have their first target moved to 2028, the 2027 target dropped and the 2030 target moved to 2032.
  • Washington DC: D.C. Code 8-1772.21 now brings private buildings of 25,000 ft² into BEPS from 1 January 2029 and 10,000 ft² from 1 January 2035. It was amended in March 2025 (D.C. Law 25-307) and again by D.C. Act 26-416 of 13 August 2026, which the Council's code site lists as a 90-day emergency amendment tied to the FY2027 budget.
  • Washington State: The first Tier 1 deadline, 1 June 2026, passed for buildings over 220,000 ft² (20,439 m²). Commerce says it is reviewing applications in order, with the largest buildings first.
  • Cambridge: The city finalised BEUDO Phase 3 regulations on 13 April 2026 and released draft Phase 3c rules on 29 June 2026.

How do penalties compare across jurisdictions?

Penalties come in three shapes. Some price each excess tonne of CO2e. Some fine per day. Some cap a payment by floor area. To compare them, we worked out the maximum each text allows for one 100,000 ft² (9,290 m²) building.

Bar charts of BPS penalties: per excess tonne CO2e NYC up to $268, Boston $234, Cambridge $234, Maryland $230 for 2030; maximum for a 100,000 sq ft building DC $1.0 million, Boston $365,000, Washington State $155,000, Cambridge $109,500, Oregon $105,000
Penalty rates as written, and AOPL arithmetic for one 100,000 ft² (9,290 m²) building. Sources: NYC Admin Code 28-320.6, Boston Code 7-2.2, Cambridge 8.67, COMAR 26.28.04.01, WA Commerce, ODOE, DOEE. Opened 13 Nov 2026.
Penalty type Where As written
Per excess tonne NYC Up to $268 per tCO2e
Per excess tonne Boston, Cambridge $234 per tCO2e (payment or credit)
Per excess tonne Maryland $230 per tCO2e for 2030, $234 for 2031, in 2020 dollars
Per day Boston $1,000 a day (35,000 ft²+) for missing the standard
Per day Cambridge Up to $300 a day after a first warning
Per floor area Washington DC Up to $10 per ft², capped at $7.5 million
Per floor area Washington State, Oregon $5,000 plus a per-ft² amount
Per energy shortfall Denver Up to $0.35 per kBtu short of target
Per violation Colorado, Montgomery County $2,000 to $5,000; $500 to $750

At ECB reference rates of 12 November 2026 ($1 = about ₹94.05), NYC's $268 per tonne is about ₹25,200. Treat the right-hand chart as an upper bound. Most texts say "up to", and Denver lets owners reinvest 40% to 80% of a penalty in retrofits if they act within 150 days.

What data does a BMS and metering system need to prove compliance?

Every programme above is decided on 12 months of metered energy. The building management system and meters are the evidence. Owners who get caught out usually have the right equipment but a weak data trail. Our building energy management system guide covers the hardware. This is what regulators actually ask for.

  1. Whole-building utility data for each fuel. Electricity, gas, steam, chilled water, oil. Most rules count district energy and on-site fuel. Maryland's law requires electric and gas companies to give owners whole-building data.
  2. A clean Portfolio Manager account. Property type, floor area and use details decide your target. Denver's rules require the profile to move to a new owner on sale.
  3. Third-party verification. Denver needs it for the 2025 or 2026 report and the 2030 target year. Seattle needs a Qualified Person every five years. Cambridge wants baseline years and the first year of each period verified. Boston can fine $1,000 to $5,000 when verified data and self-reported data don't match.
  4. Sub-metering for exclusions. Maryland excludes tenant food-service cooking and, for healthcare, labs and similar uses, sterilisation steam and emergency backup power. You can only claim that if those loads are metered separately.
  5. Interval data for retrofit proof. Hourly or 15-minute data from the BMS shows a chiller or boiler change worked before the annual number arrives.
  6. An audit file. Keep meter calibration records, BMS trend logs, invoices and change logs together.

A fault that runs for months shows up straight in a full-year EUI. Fault detection rules in the BMS earn their cost here.

Checklist: questions to ask before your next filing

  • Which jurisdiction covers the building, and is it the city, county or state? (Montgomery County buildings follow the county rule, not Maryland's.)
  • Does the gross floor area in Portfolio Manager match the one on the regulator's covered list?
  • Which metric applies, and what is your target for your property type?
  • Is every fuel and every meter in the account, including tenant meters?
  • Do you need third-party verification this year, and is a qualified verifier booked?
  • Does the BMS keep 15-minute trend data for at least 13 months?
  • Are excluded loads (kitchens, data rooms, backup generators) sub-metered?
  • What is the gap to the 2030 limit in tonnes, and what does it cost at the per-tonne rate?
  • Is an extension, alternative pathway or hardship plan open, and what is its filing date?
  • Who owns the filing: owner, property manager or tenant?

Free download: BPS Deadline Tracker (Excel)

Preview of the free BPS Deadline Tracker Excel file showing its how-to-use sheet
Free Excel tool
BPS Deadline Tracker
One filterable row per jurisdiction with the law, threshold in ft² and m², metric, next date, penalty as written and official page. Enter your floor area, city and GHG intensity to see if you are likely covered, when the next date falls and your per-tonne exposure.
  • 11 US jurisdictions checked against official texts on 13 Nov 2026
  • Coverage check, next date and days left for your building
  • Excess tonnes and indicative exposure where the rule prices CO2e
Download the free Excel file ↓
Excel (.xlsx) · Example building filled in · No sign-up

Regulation by region: how do US building performance standards compare?

Region Rule What it requires of existing buildings
US cities and states BPS laws above Measured EUI, GHG or ENERGY STAR limits, with fines
EU Directive (EU) 2024/1275 (EPBD recast), Article 9 Member states set minimum energy performance standards so non-residential buildings are below the worst 16% threshold from 2030 and the worst 26% from 2033
UK (England and Wales) MEES, interim response of 18 June 2026 Rented non-domestic buildings over 1,000 m² to reach EPC B from 2031, subject to secondary legislation
India ECSBC 2024 (BEE) Design code for new commercial buildings with 100 kW connected load or 120 kVA contract demand; no operating limit for existing buildings

The EU route is closest to a BPS. Each country sets its thresholds from its own non-residential building stock. Our EPBD Article 13 guide covers the automation rules, and the EPBD transposition tracker shows where each country stands. India's ECSBC 2024 applies at design stage, so US-style annual limits are new to most Indian owners.

What is the federal role in US building performance standards?

There is no national US building performance standard for private buildings. The rules are local. Federal support has come through tools and coalitions. On 21 January 2022 the White House announced that 33 state and local governments had joined a National Building Performance Standards Coalition. In December 2022 it announced a Federal Building Performance Standard for federal buildings, aiming for zero scope 1 emissions in 30% of federal building space by 2030. Both are now on the archived site of the previous administration. We found no current federal page confirming their status, so treat them as background. EPA's Portfolio Manager remains the common reporting tool.

If you own or run US buildings from India or elsewhere

Many Indian groups and global capability centres own or lease US space, and the filing falls to whoever the ordinance calls the owner. Three practical points:

  • The data year is the calendar year. Retrofit approvals in an April to March budget cycle can miss the year that counts.
  • The fine is in dollars and recurs. Boston, Cambridge and DC rules run every year until fixed.
  • Remote monitoring works. A cloud BMS or energy dashboard watched from India can track US meters against the target month by month. It helps when the lease says who gives meter access.

FAQs

What is the difference between benchmarking and a building performance standard? Benchmarking requires you to report energy use each year. A building performance standard requires the building to meet a limit, with penalties if it doesn't.

Which US building performance standards have deadlines in 2026 and 2027? Washington State's first Tier 1 deadline was 1 June 2026. DC's first cycle ends 31 December 2026. NYC, Cambridge, DC, Boston, Colorado, Maryland, Washington State, Denver and Montgomery County all have filings between 1 May and 1 June 2027.

What is the NYC Local Law 97 penalty? Up to $268 for each metric tonne of CO2e above the building's limit for the year (NYC Admin Code 28-320.6). Courts weigh good-faith efforts when setting the amount.

Did Maryland delay BEPS in 2026? No. The 2026 exemption bills (HB 1217, SB 479) and the repeal bill (HB 988) stopped at the hearing stage. The only 2026 law on BEPS, Chapter 412 (HB 870), adds a permit notice for new buildings and leaves the standards alone. The first emissions standard still applies from 2030 under COMAR 26.28.03.02.

Do building performance standards use ENERGY STAR Portfolio Manager? Mostly yes. EPA says all state and local benchmarking policies run on Portfolio Manager, and DC uses the ENERGY STAR score as its metric.

Is there a building performance standard in Chicago? We could not open an official Chicago text showing a performance standard today, so Chicago is not in the table.

Need help building the meter and BMS data trail for a BPS filing? See our smart building solutions or contact AOPL.