BMS Company in Delhi: What Delhi NCR Towers Need for GRAP and Energy Codes

hero background
Smart Buildings and IBMS

BMS Company in Delhi: What Delhi NCR Towers Need for GRAP and Energy Codes

Back to all blogs

Short answer: A BMS company in Delhi has to design for one airshed and three state codes. Delhi NCR's main office markets sit in Delhi, Haryana and Uttar Pradesh, and each state has its own energy code thresholds. All of them fall under CAQM's Graded Response Action Plan. Its schedule, revised on 29 September 2026, restricts diesel generators from Stage I and lets the states put offices on half strength at Stage III. Ask how a vendor's controls handle the generator rules, winter filtration and summer peaks.

This post covers Delhi NCR's office market, the energy code that applies in Delhi, Gurugram and Noida, what GRAP means for building controls, how to run a building through smog season and the summer peak, and a vendor checklist.

  • Delhi NCR leased between 3.3 and 4.19 million sq ft of office space in Q3 2026, depending on the broker (Colliers, Cushman & Wakefield and JLL, September and October 2026).
  • CAQM's GRAP schedule, revised on 29 September 2026, says diesel generator sets must not be a regular power source in the NCR. It allows older-standard diesel sets from 41 kW to under 800 kW only in dual-fuel mode or with retrofitted emission control devices (CAQM Direction No. 104).
  • Delhi's monthly average AQI was 354 in November 2025 and 351 in December 2025, and the city logged 165 days above AQI 200 that year (CAQM, 31 December 2025).
  • Uttar Pradesh's energy code, notified on 26 July 2018, covers buildings of 100 kW connected load or 120 kVA contract demand, and also plots over 1,000 m² with at least 2,000 m² built up (UP notification No. 1198).

What does a BMS company in Delhi deal with that others don't?

Three governments, one air quality regime. A tower in Cyber City, Gurugram is approved under Haryana's rules. A tower on the Noida Expressway is approved under Uttar Pradesh's rules. A campus in Aerocity or Saket answers to the Delhi government. All three sit under the Commission for Air Quality Management in NCR and Adjoining Areas (CAQM), and the same GRAP stage applies across the region, set by Delhi's AQI.

That matters for a building management system because the controls have to do three jobs that change with the season:

  • October to February: keep indoor air clean while outdoor AQI sits in the 200s and 300s, and keep diesel generators inside GRAP rules.
  • April to June: hold comfort through extreme heat while the grid hits record peaks.
  • All year: produce the meter and control evidence your state's energy code asks for.

The pollution boards that enforce GRAP on the ground in these three states are the Delhi Pollution Control Committee (DPCC), the Haryana State Pollution Control Board (HSPCB) and the Uttar Pradesh Pollution Control Board (UPPCB). Our Delhi NCR air quality monitoring post covers the station network and industry duties. This post stays on buildings.

For the general BMS architecture (controllers, field devices, BACnet, Modbus), read our building management system guide first.

How big is the office market a Delhi BMS serves?

Big, and most of it is in Gurugram. ICRA's report of 22 December 2025 puts Delhi NCR's Grade A office stock at about 204 million sq ft as of 30 September 2025, 20% of the top six cities. Gurugram holds a 60% share of the NCR market. Occupancy rose to 78.6% by September 2025, up from 72.6% in March 2023 (ICRA).

ICRA names Sector 24 (Cyber City), Sector 62 (Noida) and Sector 48 (Gurugram) as the top three micro-markets, with 17% of supply between them. It expects about 14 million sq ft of new supply in FY2026 and about 11 million sq ft in FY2027, with occupancy reaching 80.5 to 81% by March 2027.

Q3 leasing was solid. The three big brokers count Q3 2026 differently, so treat their numbers as a range:

Bar chart of Delhi NCR office leasing in Q3 2026: 4.19 million sq ft by JLL, 3.8 million by Cushman & Wakefield and 3.3 million by Colliers; ICRA puts Grade A stock at about 204 million sq ft
Delhi NCR office leasing, Q3 2026, by broker. Sources: JLL India (26 Oct 2026), Cushman & Wakefield India (13 Oct 2026), Colliers India via The Realty Today (30 Sep 2026), ICRA (22 Dec 2025).

What this means for BMS work: a large existing stock that needs control upgrades over its life, plus new supply that has to clear energy code checks. Older buildings usually do better with an integration-first approach, which our BMS retrofit guide explains.

Which energy code applies in Delhi, Gurugram and Noida?

It depends on which side of the border the plot sits. We read each state's own document and put the triggers side by side, because no official page compares them.

Delhi Haryana (Gurugram, Faridabad) Uttar Pradesh (Noida, Greater Noida, Ghaziabad)
Document Delhi ECBC 2018, published by the EE&REM Centre, Department of Power, GNCTD Notification 19/06/2016-P of 31 Mar 2016 (mandated ECBC); Haryana ECBC Rules 2022 (draft) UPECBC 2018, notification No. 1198 of 26 Jul 2018
Load trigger 100 kW connected load or 120 kVA contract demand Above 100 kW or 120 kVA and above 100 kW or 120 kVA
Area trigger Plot area of 500 m² Draft adds 500 m² conditioned area Plot over 1,000 m² with at least 2,000 m² built up
Use Commercial; private residential excluded Commercial Private residential excluded
Issuing department or agency EE&REM Centre (state designated agency) DNRE / HAREDA Additional Energy Sources Department

Sources: Delhi ECBC 2018, section 2; HAREDA ECBC page; Haryana ECBC Rules 2022 draft, code clause 2(a); UP notification of 26 July 2018 and UPECBC 2018, section 2.

Three points stand out.

Delhi's status is the least clear. The Delhi code sits on the EE&REM Centre's site, but the Centre's own ECBC page links only the 2006 national code, and we couldn't trace a Delhi Gazette notification for the 2018 text. Design to it anyway. It's the most specific document Delhi has, and its metering rules are the ones a BMS has to meet.

Haryana's newer rules are still marked draft. HAREDA's page lists the 31 March 2016 notification as the one that made ECBC mandatory, and shows the 2022 rules as a draft. The draft would also pull in any commercial building with 500 m² or more of conditioned area, whatever its load.

UP's area trigger works on plot and built-up area. A mid-size office on a 1,200 m² plot in Noida with 2,000 m² or more built up can fall under the code even with a modest load. The 2018 notification also directs that government buildings still at the design stage follow the code.

None of the three states had adopted the national Energy Conservation and Sustainable Building Code (ECSBC) in any document we could trace on 11 November 2026. Our ECSBC 2024 explainer covers what the national code adds, and it's a sensible design target for a building that will run for 25 years.

What does Delhi's code ask the BMS to measure?

Clause 7.2.4 of Delhi ECBC 2018 sets the metering, and it scales with the size of the supply:

  • Services above 1,000 kVA need permanent metering of kVA demand, kWh, total power factor, phase and neutral current, voltages and total harmonic distortion.
  • Services above 65 kVA and up to 1,000 kVA need kVA demand, kWh and total power factor.
  • Services up to 65 kVA need kWh.
  • Tenanted buildings must provide metering at a point where each tenant can connect.

Table 7-3 adds sub-metering. From 120 to 250 kVA, HVAC and renewable generation must be metered separately. Above 250 kVA, interior and exterior lighting, domestic hot water and plug loads are added. Data centres in business buildings, commercial kitchens, façade lighting and lifts carry extra requirements by building type.

The same chapter has one clause that ties straight to Delhi's air. Clause 7.2.3 says DG sets in buildings above 20,000 m² built-up area must carry at least a 3-star BEE rating in an ECBC building, 4-star for ECBC+ and 5-star for SuperECBC. It also recommends gas-based generators to stay in line with GRAP when it comes into action, and notes that BEE has no star rating for gas generators yet.

A BMS that only shows chiller graphics won't pass this. You need the meter schedule mapped to clause 7.2.4 and Table 7-3 before design freeze. Our posts on sub-metering and BMS cost show how meters drive the points count and the budget.

What does GRAP mean for a building's power and controls?

More than most owners expect. CAQM issued the current schedule through Direction No. 104 on 29 September 2026, under section 12 of the CAQM Act, 2021 (CAQM Direction No. 104). The stages are keyed to Delhi's AQI: Stage I at 201 to 300, Stage II at 301 to 400, Stage III at 401 to 450 and Stage IV above 450. Each stage adds to the ones before it (GRAP schedule, revision 29.09.2026).

Three items reach directly into a commercial building.

Generators, from Stage I. Item 17 says DG sets must not be used as a regular source of power. Item 18 applies "regulated operations of DG sets" to industrial, commercial and residential users, following CAQM Direction No. 76 of 29 September 2023:

DG set size What the set needs Use allowed
Any size on natural gas, LPG, biogas, propane or butane Nothing extra No restrictions
Up to 800 kW (1,000 kVA) built to GSR 804(E) of 3 Nov 2022 Nothing extra No restrictions
800 kW (1,000 kVA) and above, older standard An emission control system that meets Direction No. 76 limits No restrictions
41 kW (51 kVA) to under 800 kW, older standard Dual-fuel mode or retrofitted emission control devices from certified agencies No restrictions
19 kW (23 kVA) to under 41 kW Dual-fuel mode No restrictions
Below 19 kW (23 kVA), portable No control available Emergency services only

Source: CAQM GRAP schedule, revision 29.09.2026, Stage I item 18.

Sets that aren't in dual-fuel mode only because gas isn't available are limited to prescribed emergency services. That list includes lifts and escalators, hospitals, and telecom and IT or data services.

For a BMS this means logging which set ran, for how long, at what load and on which fuel, so the facility team can show compliance when an inspector asks. Ask whether the DG controller can report fuel mode and emission device status, not just run status.

Office timings, from Stage II. Item 7 asks the Delhi government and NCR states to stagger timings for public offices in Delhi, Gurugram, Faridabad, Ghaziabad and Gautam Buddha Nagar.

Half-strength offices, at Stage III. Item 9 leaves it to the NCR states and the Delhi government to decide whether public, municipal and private offices work at 50% strength with the rest from home.

Schedules have to follow occupancy. A BMS that still runs every floor's AHUs from 8 am to 8 pm when half the staff are at home is burning money. Zone-level schedules, occupancy sensing and a "GRAP mode" the facility manager can switch on in one step pay off here.

How should a BMS run through Delhi's smog season?

Treat it as a filtration season, not a ventilation one. CAQM's year-end release for 2025 shows Delhi's monthly average AQI above 200 from October to February (and in April, at 210), peaking at 354 in November and 351 in December (CAQM press release, 31 December 2025). The year had 157 days in the "Poor" to "Very Poor" band and 8 days at "Severe" or worse. The 2025 annual average was 201, the lowest since 2018 apart from 2020.

Line chart of Delhi monthly average AQI in 2025, from 78 in July to 354 in November and 351 in December, over the 2018-2025 range, with GRAP Stage I (201-300) and Stage II (301-400) bands shaded
Delhi monthly average AQI, 2025 and the 2018-2025 range, against GRAP stage bands. Sources: CAQM press release, 31 Dec 2025; CAQM GRAP schedule, revision 29.09.2026.

Plotting eight years of CAQM's month-wise data shows the pattern doesn't shift much. November averages ranged from 312 to 377 between 2018 and 2025. July and August sat below 120 in all but one month (July 2019, 134).

What a well-set-up Delhi BMS does in those months:

  • Watches outdoor PM2.5 and indoor PM2.5 together. One outdoor sensor at the fresh-air intake and indoor sensors per zone let the system show filter performance as a number, not a guess.
  • Runs fresh air on CO₂, not on a fixed damper position. Demand-controlled ventilation brings in only the outside air the occupancy needs. Our CO₂ sensor guide explains the sensors.
  • Tracks filter pressure drop. Fine filters load fast in November. Differential pressure alarms tell the team when to change them before airflow drops.
  • Logs indoor air quality for tenants. A floor-level IAQ record answers tenant questions with data during smog weeks. Our indoor air quality post covers what to measure and what targets to set.

Watch the energy side too. Higher-grade filters add fan pressure. The BMS should show fan kW against filter pressure so the team can see what clean air costs.

What does the summer peak mean for building controls?

Delhi's demand curve turns upside down in summer. Peak power demand hit a record 8,748 MW at 3:17 pm on 29 June 2026, beating the earlier record of 8,656 MW set on 19 June 2024 (Construction World, 3 July 2026).

An afternoon peak in a city where offices run on chillers means three things for the BMS:

  • Demand limiting. The kVA metering Delhi's code already requires above 65 kVA gives you the data. Set a demand limit and shed non-critical loads in steps when the building approaches it.
  • Chiller sequencing. Run the most efficient combination of chillers and pumps for the load, not a fixed lead-lag. Our chiller plant optimisation post explains the logic.
  • Fewer DG hours. Every outage hour moves load onto generators, which brings GRAP-era rules and fuel costs back into play. Tie the BMS to the main incomer and the DG panels so changeovers and run hours are recorded automatically.

Check your own DISCOM bill for the tariff and any time-of-day terms that apply. Delhi, Haryana and UP have different regulators and different schedules, so a vendor's savings claim should use your bill, not a generic rate.

Which fire rule brings fire-BMS integration into play in Delhi?

Height and occupancy. Rule 27 of the Delhi Fire Service Rules, 2010 lists the buildings treated as a fire risk under section 25 of the Delhi Fire Service Act. Business buildings are covered above 15 m or at ground plus four upper storeys, including any mezzanine. Mercantile buildings are covered above 9 m or ground plus two, and all assembly buildings are covered (Delhi Fire Service Rules, 2010). Ask your architect to confirm you have the current text.

Almost every office tower in Delhi crosses that line. Haryana and UP run their own fire laws, so a Gurugram or Noida project follows a different approval route. Either way, the fire alarm panel should talk to the BMS for AHU shutdown, stair pressurisation, lift homing and door release. Our post on connecting fire, access, CCTV and lifts covers how to specify the interfaces.

What should you ask a BMS company in Delhi before you sign?

Ask each bidder for evidence, not adjectives. This list follows the Delhi NCR issues above.

State code and metering

  1. Which code applies to our plot: Delhi ECBC 2018, Haryana's 2016 notification (or the 2022 draft), or UPECBC 2018? Show us the trigger you used.
  2. Can you map every meter to Delhi ECBC clause 7.2.4 and Table 7-3, or the equivalent UP or Haryana clause?
  3. Will tenants get their own metering points and a read-only data feed?

GRAP and generators

  1. Will the BMS log DG run hours, load, fuel mode and emission control device status for each set?
  2. Can the facility manager switch the building to a GRAP schedule (reduced occupancy, staggered start) in one step?
  3. If the DG sets are older diesel units from 51 kVA to under 1,000 kVA, who handles the retrofit or dual-fuel kit, and how does the BMS read it?

Air quality

  1. Where will outdoor and indoor PM2.5 and CO₂ sensors go, and how will you calibrate them?
  2. Do you use filter differential pressure alarms and fan kW trending?

Summer peak and platform

  1. How does the demand-limit sequence work, and which loads shed first?
  2. Is the platform open (BACnet, Modbus), and do we get programs, graphics, licences and passwords at handover? Our platform comparison gives a neutral view of the main brands.
  3. How is the BMS network separated from corporate IT? See our post on building systems cybersecurity.
  4. What response times do you commit to for Delhi, Gurugram and Noida sites under the AMC?

A bidder who can answer the first six with documents from a past NCR project is worth a site visit.

FAQs

Does the energy code apply to my building in Noida? If it has 100 kW connected load or 120 kVA contract demand, or sits on a plot over 1,000 m² with at least 2,000 m² built up, UPECBC 2018 covers it. Private residential buildings are excluded.

Has Haryana replaced its 2016 ECBC notification? HAREDA still lists the Haryana ECBC Rules 2022 as a draft. The 31 March 2016 notification is the one its page cites as making ECBC mandatory.

Can I run a diesel generator in my Gurugram office during GRAP? Yes, as backup but not as a regular power source (Stage I item 17), and only if it meets the regime in item 18. An older-standard set from 51 kVA to under 1,000 kVA needs dual-fuel mode or a retrofitted emission control device. Gas sets have no restriction.

At what GRAP stage can offices be asked to work at half strength? At Stage III (Delhi AQI 401 to 450), item 9 lets the NCR states and the Delhi government decide whether public, municipal and private offices run at 50% strength.

How many bad air days did Delhi have in 2025? CAQM counted 157 "Poor" to "Very Poor" days and 8 "Severe" or worse days, 165 days above AQI 200 in all.

Planning a BMS for an office, hospital, hotel or campus in Delhi, Gurugram or Noida? Asset Online Pvt Ltd (AOPL) works with clients across India and supplies and integrates solutions in this area. See our smart buildings solutions or contact us.

Sources

  • Commission for Air Quality Management in NCR and Adjoining Areas, Direction No. 104, Revised Schedule of the Graded Response Action Plan for NCR, 29 September 2026: direction PDF
  • CAQM, Graded Response Action Plan for NCR, revision 29.09.2026: GRAP schedule PDF
  • CAQM, press release "2025 - Air Quality Perspective in Delhi", 31 December 2025: press release PDF
  • EE&REM Centre, Department of Power, Government of NCT of Delhi, Delhi Energy Conservation Building Code 2018: code PDF
  • HAREDA, ECBC and ENS (Buildings) page: HAREDA
  • DNRE / HAREDA, Haryana Energy Conservation Building Code Rules, 2022 (draft): draft rules PDF
  • Government of Uttar Pradesh, Additional Energy Sources Department, notification No. 1198/87-Add. Energy Sources Deptt.-2018, 26 July 2018, and UPECBC 2018 (English translation, copy hosted on thc.nic.in): notification and code PDF
  • Government of NCT of Delhi, Delhi Fire Service Rules, 2010: rules PDF
  • ICRA, Office occupancy in Delhi NCR expected to surpass 80% for the first time by March 2027, 22 December 2025: report summary
  • JLL India, India's office gross leasing hits a record, 26 October 2026: press release
  • Cushman & Wakefield India, India office market growth in Q3 2026, 13 October 2026: press release
  • The Realty Today, India office space demand reaches 54.4 million sq ft in Jan-Sep 2026: Colliers India report, 30 September 2026: article
  • Construction World, Delhi peak power demand reaches 8,748 MW record, 3 July 2026: article