Short answer: An air quality monitoring system in Delhi NCR works inside one shared rulebook. The Commission for Air Quality Management (CAQM) triggers GRAP off Delhi's AQI, and the NCR's 84 reference stations are being expanded to 157. Industry duties apply all year: approved fuels only, a 50 mg/Nm³ particulate limit since 1 October 2026, OCEMS, and PTZ cameras on stacks and fuel points by 30 November 2026. GRAP stages then tighten DG sets, crushers, mining and construction.

This post covers the station network across the four NCR states, the GRAP schedule revised on 29 September 2026, the CAQM directions that bind plants, and a pre-winter readiness checklist.

  • CAQM counted 84 continuous ambient air quality monitoring stations (CAAQMS) in NCR in February 2026: 40 in Delhi, 22 in Haryana, 18 in Uttar Pradesh and 4 in Rajasthan, with 157 planned (CAQM press release, 10 Feb 2026).
  • CAQM Direction No. 104 dated 29.09.2026 issued the current GRAP schedule, with four stages keyed to Delhi's AQI: 201-300, 301-400, 401-450 and above 450 (CAQM).
  • Direction No. 98, as amended on 30.07.2026, sets a 50 mg/Nm³ stack PM limit for 17 CPCB categories, Red medium and large units, and food, textile and metal units with boilers or furnaces from 01.10.2026 (CAQM).
  • A CAQM order of 16 October 2026 requires those same industries to stream PTZ camera feeds of fuel-feeding points, stacks and OCEMS ports to CPCB and the state board by 30.11.2026 (CAQM press release, 16 Oct 2026).
  • By AOPL's count of CAQM orders, NCR spent 153 days under GRAP in winter 2025-26, including 27 days at Stage III and 14 at Stage IV.

What makes air quality monitoring in Delhi NCR different?

In Delhi NCR, one statutory body sets air rules across four states. Section 12 of the CAQM Act, 2021 lets the Commission issue binding directions to any person or authority, so a plant in Manesar, Bhiwadi, Sahibabad or Okhla answers to its state board and to CAQM at once.

That has three practical effects.

  1. Four boards, one trigger. The Delhi Pollution Control Committee (DPCC), Haryana State Pollution Control Board (HSPCB), Uttar Pradesh Pollution Control Board (UPPCB) and Rajasthan State Pollution Control Board (RSPCB) all enforce the same GRAP stage. That stage is set by Delhi's AQI, not by your district's own reading.
  2. Rules arrive as numbered directions. Fuel lists, emission limits and DG rules sit in them, and they change often. The count reached No. 104 in September 2026.
  3. Enforcement is fast. As of 16 October 2026, CAQM's flying squads had inspected 28,868 units, projects and entities across NCR and issued 1,837 closure directions, of which 1,491 were later lifted after compliance was verified (CAQM, 141st ETF meeting, 17 Oct 2026).

For NCAP and the national network, read our guide to air quality monitoring in India. This post sticks to what is specific to NCR.

How many air quality monitoring stations does Delhi NCR have?

CAQM's own count, released on 10 February 2026, was 84 existing CAAQMS: 40 in Delhi, 22 in Haryana-NCR, 18 in Uttar Pradesh-NCR and 4 in Rajasthan-NCR. Another 27 were being added (6 in Delhi, already installed, plus 7, 10 and 4 in the other states). CAQM then said a further 46 were needed, which would take the network to 157 (CAQM press release, 10 Feb 2026).

Stacked bar chart of CAAQMS by NCR state: Delhi 40 existing, 6 being added, 14 further required, 60 planned; Haryana 22, 7, 16, 45 planned; Uttar Pradesh 18, 10, 15, 43 planned; Rajasthan 4, 4, 1, 9 planned; 84 existing and 157 planned in total
Continuous ambient air quality monitoring stations in Delhi NCR by state. Sources: CAQM press release, 10 Feb 2026; PIB, 15 May 2026.

The 157 figure comes from a new siting norm. Delhi and the contiguous cities of Ghaziabad, Noida, Greater Noida, Gurugram, Faridabad and Sonipat get roughly one station per 25 sq km (a 5 km by 5 km grid). Other district headquarters and towns get one per 50 sq km. The full Commission reviewed progress on 15 May 2026 and asked the states to speed up installation (PIB, 15 May 2026).

CPCB's station list for Delhi-NCR shows Delhi's network split between DPCC (24 stations), IMD (8) and CPCB (6), with HSPCB, UPPCB and RSPCB running most stations in their NCR districts (CPCB CAAQMS list for Delhi-NCR). That list dates from November 2020, so treat the split as indicative.

Enforcement is uneven too. Reviewing Stage III and IV last winter, CAQM found shortfalls of 7% to 99.6% across key actions by DPCC and the state boards (CAQM press release, 19 Jan 2026).

What did Delhi's AQI look like in 2025?

Delhi's annual average AQI was 201 in 2025, the lowest since 2018 apart from the COVID year 2020, according to CAQM. The city had 79 days with AQI of 100 or below and 8 days in the 'Severe' or 'Severe+' range (CAQM, 2025 air quality perspective, 31 Dec 2025). Annual average PM2.5 was 97 µg/m³ and PM10 was 198 µg/m³ (CAQM, 2 Jan 2026).

Bar chart of Delhi's monthly average AQI in 2025 against GRAP bands: January 306, February 214, April 210, October 223, November 354 and December 351 in the Stage I or II bands; July 78 and August 89 the lowest
Delhi month-wise average AQI, 2025, with GRAP stage bands. Source: CAQM press release, 31 Dec 2025; GRAP schedule revision 29.09.2026.

In 2025, November averaged 354 and December 351, both inside the Stage II band, while July and August dropped below 100. Monthly averages hide daily spikes, which is why Stage III and IV still came into force for several weeks.

An independent view from the Centre for Research on Energy and Clean Air puts Delhi's 2025 PM10 average at 197 µg/m³, the highest in India and three times the national standard. It also says Delhi had used about 33% of the clean air funds allocated to it under NCAP (CREA, NCAP progress report, January 2026).

What are the GRAP stages in the September 2026 schedule?

CAQM issued the current schedule through Direction No. 104 on 29 September 2026, with immediate effect (CAQM Direction No. 104). It replaces the schedule of 21 November 2025 (GRAP schedule, revision 29.09.2026).

Stage Delhi AQI Number of actions Examples that touch businesses
I, 'Poor' 201-300 25 Approved fuels and emission norms enforced; DG sets only under Direction 76; dust portal compliance for C&D sites of 500 sq m or more
II, 'Very Poor' 301-400 8 Targeted action at pollution hotspots; more C&D inspections; staggered public office timings
III, 'Severe' 401-450 10 Dust-generating C&D stopped; stone crushers and mining closed; states decide on 50% work from home
IV, 'Severe+' Above 450 5 Truck entry stopped except LNG, CNG, electric and BS-VI diesel; states may close non-emergency commercial activity

Three rules in the preamble matter:

  • Stages are invoked in advance, based on IMD and IITM forecasts, not only after the AQI crosses a line.
  • Each stage adds to the earlier ones. At Stage III, all Stage I and II actions still apply.
  • CAQM's Sub-Committee on GRAP issues each invocation as a separate order.

Where things stand on 30 October 2026: the latest order on CAQM's GRAP orders page invoked Stage I across NCR on 21 October 2026. Delhi's AQI had risen from 179 on 20 October to 244 at 2 pm on 21 October (CAQM order, 21 Oct 2026). Check the orders page daily from now to February.

To see what a winter looks like, we counted the days at each stage from every CAQM invocation and revocation order between 14 October 2025 and 16 March 2026.

Timeline of the GRAP stage in force in Delhi NCR from 14 October 2025 to 15 March 2026: 153 days in total, Stage I 31 days, Stage II 81 days, Stage III 27 days and Stage IV 14 days
GRAP stage in force across NCR, winter 2025-26, counted by AOPL from CAQM invocation and revocation orders.

Stage II was the norm, at 81 days. Stage III and IV together covered 41 days in three spells. Plan for about three months of Stage II with short Stage III or IV episodes in between.

What must industry do at each GRAP stage?

No single official document lays this out, so we built it. The table pulls the industry-facing items out of the 29.09.2026 schedule and lines them up with the standing CAQM directions they refer to.

Stage What applies to a plant or facility Rule behind it
All year Use only fuels on CAQM's approved list. In Delhi, industry runs on PNG or electricity only Direction No. 65 (23.06.2022, addendum 03.04.2023); Direction No. 53
All year Stack PM at or below 50 mg/Nm³ for covered industries Direction No. 98 (20.02.2026, amended 30.07.2026)
All year OCEMS installed and connected; PTZ cameras on fuel points, stacks and OCEMS ports by 30.11.2026 CPCB directions of 01.10.2025 and 09.10.2025; CAQM order of 16.10.2026
Stage I Intensified inspections, including in non-conforming areas; strict penal action on non-compliant units GRAP Stage I, items 12 and 13
Stage I DG sets not used as a regular power source; operation only as per Direction 76 GRAP Stage I, items 17 and 18; Direction No. 76 (29.09.2023)
Stage I Industrial and hazardous waste lifted regularly; no open dumping or burning GRAP Stage I, items 3 and 6
Stage I Thermal power plants within 300 km of Delhi held to emission norms GRAP Stage I, item 14
Stage II Targeted action on the dominant source in each hotspot, which can include industrial clusters GRAP Stage II, item 3
Stage III Stone crushers and mining closed; most dust-generating construction stopped (see our construction dust post) GRAP Stage III, items 1 to 3
Stage III States decide on 50% office attendance; BS-III petrol and BS-IV diesel cars restricted in Delhi and high-density districts GRAP Stage III, items 4 and 9
Stage IV Goods vehicles other than LNG, CNG, electric or BS-VI diesel cannot enter Delhi; states may close non-emergency commercial activity GRAP Stage IV, items 1, 2 and 5

There's no blanket industry shutdown in Stage III or IV. Neither the November 2025 nor the September 2026 schedule closes general industry at the higher stages. CAQM has moved the load into all-year rules. A compliant plant rides out Stage IV with logistics problems; a non-compliant one can be shut on any day.

DG sets are regulated at Stage I. Under the schedule's table, gas-based sets of any size and sets up to 800 kW built to the GSR 804(E) standard of 03.11.2022 have no restriction. Older diesel sets of 19 kW to under 800 kW need dual-fuel mode or a retrofitted emission control device (dual-fuel only, below 41 kW). Portable sets under 19 kW are allowed only for listed emergency services, which include lifts, hospitals, metro, sewage plants and telecom and IT or data services (GRAP schedule, Stage I, item 18). In the 15 days to 9 October 2026, the CAQM Enforcement Task Force logged 64 DG set inspections and 15 violations.

Which CAQM directions apply to NCR industries all year?

Direction No. 65: approved fuels. Issued on 23 June 2022 and updated by an addendum on 3 April 2023, it sets one list of approved fuels for the whole NCR and says every other fuel is "unapproved" in NCR. The list covers natural gas, LPG, electricity, BS-VI fuels, biofuels and a few specific uses. Biomass, metallurgical coke for cupolas and low-sulphur fuel oils for furnaces are allowed only outside Delhi (CAQM Direction No. 65).

Direction No. 98: the 50 mg/Nm³ PM limit. Issued on 20 February 2026, it tightened stack particulate limits from 80 mg/Nm³ (the old figure for biomass boilers and furnaces) to 50 mg/Nm³. It covers the 17 CPCB categories, Red category medium and large units, food processing and textile units with boilers or thermic fluid heaters, and metal units with furnaces (CAQM Direction No. 98). The CPCB committee behind it said new or upgraded pollution control devices should come only from National Productivity Council empanelled vendors. After industry cited long APCD lead times and too few recognised labs, CAQM moved the date for all covered units to 1 October 2026 (amendment to Direction No. 98). That date has passed.

OCEMS. CPCB directions dated 1 and 9 October 2025 require online continuous emission monitoring in the same industry groups in NCR. CAQM set up an OCEMS Cell, which by February 2026 had verified installations at 865 units and recommended notices in 530 cases (CAQM, OCEMS status, 8 Feb 2026). Our OCEMS explainer covers the analysers and CPCB connectivity.

PTZ camera order, 16 October 2026. Industries covered by Direction 98 must install pan-tilt-zoom cameras at every fuel-feeding or charging point of boilers, heaters, furnaces and kilns, on gas meters where gas is used, on stacks and OCEMS sampling ports, and on fume extraction areas. Feeds go live over RTSP to CPCB and state board servers, with power backup, by 30 November 2026 (CAQM press release, 16 Oct 2026). CAQM said flying squads had found units burning unapproved fuels.

Where does each NCR state stand?

Combining CAQM's station count with its OCEMS status release gives a state-by-state view that no single official document shows.

NCR state Regulator CAAQMS now (Feb 2026) CAAQMS planned Units required to install OCEMS OCEMS installed or ordered (8 Feb 2026) Share
Delhi DPCC 40 60 128 57 45%
Haryana (NCR) HSPCB 22 45 907 905 99.8%
Uttar Pradesh (NCR) UPPCB 18 43 648 320 49%
Rajasthan (NCR) RSPCB 4 9 255 145 57%
Total 84 157 1,938 1,427 74%

Sources: CAQM press releases of 10 Feb 2026 and 8 Feb 2026. Share is AOPL's calculation.

Haryana's NCR districts had almost every listed unit on OCEMS by February; Delhi and UP-NCR were under half. CAQM said units that had taken no action would be proposed for closure. In Ghaziabad, Gautam Buddh Nagar, Bhiwadi or Delhi's industrial areas, expect inspectors to check the stack monitor, camera feed and fuel bills together.

Does an NCR plant need its own air quality monitoring system?

Usually yes, but be clear which kind. For a plant it can mean three things:

  • Ambient monitoring at the boundary. Your consent to operate from DPCC, HSPCB, UPPCB or RSPCB may require it; check the CTO. Our CPCB guidelines checklist covers siting and methods for reference-grade monitoring.
  • Stack monitoring. This is where NCR rules bite hardest: OCEMS and proof of the 50 mg/Nm³ limit. Manual isokinetic tests still matter for audits; see stack sampling vs CEMS.
  • Fenceline sensors for early warning. Low-cost PM sensors don't replace reference monitors, but they flag your own dust or smoke before an inspector does. Our sensor guide explains what they can and can't do.

With GRAP keyed to Delhi's average, your own boundary data is the best answer to a complaint about your site. For budgets, see our AQMS price guide.

Site-readiness checklist for an NCR plant before peak winter

Run this in November, before the worst weeks.

  1. Fuel. Every fuel on site is on the Direction 65 list for your location, and purchase records match.
  2. Stack limit. Latest stack test shows PM at or below 50 mg/Nm³ for every covered boiler, heater and furnace. APCD upgrades are complete and documented.
  3. OCEMS. Analysers are calibrated, data reaches the CPCB portal, and you have an outage log ready to show.
  4. PTZ cameras. Cameras cover fuel-feeding points, gas meters, stacks, OCEMS ports and fume extraction, with night visibility and UPS backup. RTSP streams are tested before 30 November 2026.
  5. DG sets. Each set is listed by kW rating with its Direction 76 status: gas, GSR 804(E) compliant, dual-fuel or retrofitted. Non-compliant sets are tagged for emergency use only.
  6. Waste. Industrial and hazardous waste lifting is scheduled. No burning on site or in the yard.
  7. Construction on site. Any project of 500 sq m or more is registered on the state dust portal, and a Stage III stop plan is ready.
  8. Logistics. BS-VI, CNG, LNG or electric trucks are lined up for Delhi deliveries under Stage IV.
  9. People. A Stage III plan for 50% office attendance is ready.
  10. Watch list. Someone checks CAQM's GRAP orders page and Delhi's AQI forecast every morning from October to February.

Questions to ask a vendor in Delhi NCR

  • Can your OCEMS and PTZ setup push data to the CPCB and DPCC or SPCB servers today? Show a live NCR site.
  • Are you, or your APCD partner, on the National Productivity Council empanelled list that CPCB's committee referred to?
  • What's your response time for a camera or analyser fault, given that outages must be reported to the board?
  • Who owns the data, and can we export a full year for an inspection or a court reply?

Asset Online Pvt Ltd (AOPL) supplies and integrates solutions in this area and works with clients across India.

FAQs

Which GRAP stage is in force in Delhi NCR now? As of 30 October 2026, the latest CAQM order invoked Stage I on 21 October 2026, when Delhi's AQI reached 244. CAQM can move to a higher stage at a day's notice, so check its GRAP orders page.

Does GRAP Stage IV shut down factories in NCR? Not as a blanket rule under the 29.09.2026 schedule. Stage III closes stone crushers and mining. Factories are mainly controlled through all-year rules on fuels, emissions and monitoring.

What is the PM emission limit for industries in Delhi NCR? 50 mg/Nm³ for covered industries from 1 October 2026, under CAQM Direction No. 98 as amended on 30 July 2026. Units already holding a tighter limit in their consent keep that tighter limit.

How many air quality monitoring stations are there in Delhi? CAQM counted 40 CAAQMS in Delhi in February 2026, with 6 more installed then and a target of 60. Across NCR the count was 84, with 157 planned.

Can I run a diesel generator during GRAP? Yes, within limits. Gas sets and GSR 804(E) sets up to 800 kW are unrestricted; older sets need dual-fuel or a retrofitted control device.

Planning monitoring for an NCR plant this winter? Talk to AOPL or see our environmental intelligence solutions.