Short answer: in Delhi, every construction or demolition project on a plot of 500 sq m or more must register on the DPCC dust portal, install low-cost PM2.5 and PM10 sensors linked to a live cloud dashboard, run video fencing of the site, and file a self-audit every 15 days. Larger sites also need anti-smog guns by built-up area. Across NCR, GRAP Stage III bans most dust-making work when Delhi's AQI is severe. Other states follow national dust rules under G.S.R. 94(E) of 2018.
This guide covers what the rules say, how site dust monitoring works, what to buy, and what to ask a vendor. It's written for project heads, EHS managers and contractors.
Which rules apply to construction dust in India?
Four layers of rules apply, from national to NCR-specific:
| Layer | Instrument | What it does |
|---|---|---|
| National | Environment (Protection) Amendment Rules, G.S.R. 94(E), effective 25 Jan 2018 | Adds dust mitigation measures for construction, in cities where PM10 or PM2.5 exceeds national standards |
| NCR | Commission for Air Quality Management (CAQM) directions, applied in Delhi through the DPCC portal | Dust portal registration, sensors and video fencing for projects of 500 sq m or more |
| NCR | Graded Response Action Plan (GRAP) | Bans or restricts C&D work in stages as Delhi's AQI worsens |
| Courts | Supreme Court and NGT orders | Anti-smog guns on large sites; environmental compensation for violations |
G.S.R. 94(E) inserted two entries into Schedule I of the Environment (Protection) Rules, 1986 (SCC Online, 9 Mar 2018). Entry 106 covers projects that need environmental clearance. They need an approved environmental management plan with dust measures, paved and blacktopped roads at the site, covered loose material, a wind-breaker one-third of the building height (up to 10 m), a water sprinkling system, and a public display of the dust measures. Entry 107 applies to all construction and demolition: no grinding or cutting in the open, no roadside storage of materials, and no uncovered vehicles carrying material or debris.
What must a Delhi construction site do?
The Delhi Pollution Control Committee (DPCC) runs the dust control self-assessment portal. According to its FAQ (DPCC dust portal FAQs):
- Register if the plot area is 500 sq m or more. Smaller projects must still follow dust guidelines but don't register.
- Install low-cost PM2.5 and PM10 sensors at the site, linked to cloud storage with a live dashboard on the portal.
- Video fencing: cameras with remote connectivity covering the full project area, with the live camera URL entered on the portal so DPCC can watch in real time.
- Self-audit: submit the self-audit assessment sheet every 15 days.
- Anti-smog guns on larger sites, by built-up area:
The Delhi Environment Department's notice lists 14 dust mitigation measures for every C&D site in Delhi (Department of Environment, GNCTD). These include wind-breaking walls, tarpaulin or green net on scaffolding, wheel washing, covered vehicles, wet jet cutting, water sprinkling, on-site recycling or authorised disposal of C&D waste with records, dust masks for workers, and a public display board. Anti-smog guns and paved, blacktopped roads are listed for sites above 20,000 m² built-up area. The notice says failure to comply can lead to environmental compensation as prescribed by the NGT and stoppage of work.
Outside Delhi, check with your state pollution control board for its own portal, form and sensor rules.
What happens under GRAP?
GRAP is a set of actions that kick in as Delhi's air quality worsens. Under the schedule as revised in 2024, Stage II covers "very poor" air (Delhi AQI 301 to 400) and Stage III covers "severe" air (AQI 401 to 450) (Lexplosion summary of the revised GRAP schedule, 28 Sep 2024). At Stage III, dust-generating C&D work is banned across NCR. That includes excavation and filling, piling, open-trench utility work, brick and masonry, RMC batching plants, cement and plaster work, tile cutting, road construction and moving material on unpaved roads. Railways, metro, airports, hospitals, defence, linear public projects and sanitation projects are exempt, subject to dust norms.
CAQM modified the schedule again in November 2025. When it revoked Stage III on 22 January 2026, it also said that C&D sites closed for violations cannot restart without a specific order from the Commission (PIB, 22 Jan 2026). Read the current GRAP schedule on CAQM's website before each winter, because the stage rules change.
This is the real business case for monitoring. A site that can show clean data and good controls is less likely to face closure orders, and its records hold up in an inspection.
How does construction site dust monitoring work?
A typical site setup has four parts:
- PM sensors at the boundary. Low-cost optical sensors measure PM2.5 and PM10 every few minutes. Place at least one on the side facing the nearest homes or road, and one upwind as a reference, so you can tell site dust from background pollution.
- Gateway and cloud. Sensor data goes over 4G to a cloud dashboard, and from there to the state portal where it's required.
- Video fencing. IP cameras covering the whole site, with a live link shared with the regulator.
- Actions linked to readings. When PM10 at the boundary rises above your trigger, the site supervisor gets an alert and turns on sprinklers or the anti-smog gun, or stops the dusty task.
Low-cost sensors need care. They read high in humid air and drift over time, so ask for local calibration against a reference monitor. Our air quality sensors guide explains the sensor types and their limits, and our CPCB ambient air monitoring checklist covers reference-grade monitoring.
What does a site dust monitoring system include?
| Item | What to specify |
|---|---|
| PM sensor unit | PM2.5 and PM10, with temperature and humidity; outdoor enclosure; solar or mains power |
| Connectivity | 4G gateway with local buffering so no data is lost during outages |
| Dashboard | Live and historical data, alarms, export for the portal and inspections |
| Portal link | Data push to the state dust portal in its required format |
| Cameras | Weatherproof IP cameras, coverage of all boundaries, remote live view |
| Controls | Optional relay output to start sprinklers or the anti-smog gun on high readings |
| Service | Calibration, cleaning, data uptime reports, replacement within a set time |
See our dust and particulate monitoring range and environmental intelligence solutions for the hardware and platform.
What does it cost, and what's the payback?
Costs depend on the number of monitoring points, the camera count and the service period. Ask for a quote broken into sensor units, cameras, gateway, dashboard subscription and annual service, so you can compare vendors line by line.
The payback isn't about energy. It's about avoided risk:
- Stoppage risk. A closure order on a large site stops labour, equipment and finance clocks together.
- Compensation. Environmental compensation for violations is levied per the NGT's framework.
- Evidence. Continuous data and video show you met the rules on the day an inspector or a neighbour complains.
- Neighbour relations. Live dust data helps settle complaints with facts.
Checklist: questions to ask a dust monitoring vendor
- Can your system push data to our state's dust portal in the required format today? Show a live site.
- How are the sensors calibrated, and how often? Can you show a comparison with a reference monitor in a similar climate?
- What happens to data during a network outage, and how much can the device buffer?
- How many monitoring points do you recommend for our plot, and where?
- Can the system trigger sprinklers or anti-smog guns automatically?
- What's your uptime commitment and replacement time for a failed unit?
- Who owns the data, and can we export it for audits?
FAQs
Which construction sites must register on the dust portal? In Delhi, all construction and demolition projects with a plot area of 500 sq m or more. Outside Delhi, check your state board's rules.
Are PM sensors mandatory at construction sites? In Delhi, yes, for projects of 500 sq m or more: low-cost PM2.5 and PM10 sensors linked to a cloud dashboard on the portal.
When do anti-smog guns become mandatory? DPCC requires them by built-up area, starting with one gun for sites of 5,000 to 10,000 sq m and rising to four for 20,001 to 30,000 sq m. The Delhi Environment Department's notice lists them for sites above 20,000 m².
Does GRAP stop all construction? No. At Stage III, dust-generating C&D work stops across NCR, but exempt categories such as metro, railways, hospitals and some public projects can continue under strict dust norms.
What about cities outside NCR? G.S.R. 94(E) applies dust measures in cities where PM10 or PM2.5 exceeds national standards. State boards and city authorities can add their own conditions.
Need dust monitoring for a construction site? Talk to our environmental team.
Sources
- Environment (Protection) Amendment Rules, 2018, G.S.R. 94(E), entries 106 and 107 of Schedule I: SCC Online summary
- Delhi Pollution Control Committee, dust control self-assessment portal FAQs: DPCC
- Department of Environment, Govt. of NCT of Delhi, Dust Mitigation Measures for Construction and Demolition Activities: notice
- Press Information Bureau, CAQM revokes Stage III restrictions across Delhi-NCR, 22 Jan 2026: PIB
- Lexplosion, CAQM revises GRAP schedule, 28 Sep 2024: summary