IT Infrastructure in Delhi NCR: Noida and Gurugram Data Centres and UP Policy

hero background
IT Infrastructure

IT Infrastructure in Delhi NCR: Noida and Gurugram Data Centres and UP Policy

Back to all blogs

Short answer: IT infrastructure in Delhi NCR now runs through Noida and Greater Noida. That cluster held 86% of the region's 182 MW of operational data centre capacity at the end of 2025 (Cushman & Wakefield). UP's Data Centre Policy 2026 targets 2 GW more, and Haryana notified its own policy in May 2026. If you're choosing a data center company in India for an NCR workload, check power, DG compliance under GRAP and connectivity before price.

This post covers NCR capacity, the UP and Haryana policies, GRAP rules for diesel generators, power options, colocation versus on-premise, and a vendor checklist.

  • Delhi NCR had 183 MW of operational data centre capacity and 387 MW of future supply in H1 2026 (Cushman & Wakefield, 23 September 2026).
  • The UP Data Centre Policy 2026, notified by G.O. dated 9 July 2026, targets 2 GW+ of additional capacity and over ₹2 lakh crore of investment (UP Department of IT & Electronics).
  • Under the earlier UP policy, 133 MW from 7 of 8 listed projects had been commercialised (UP Electronics Corporation, checked 24 October 2026).
  • The Haryana Data Centre Policy 2026, notified on 27 May 2026, offers up to 20% capex reimbursement for data centres above 10 MW (Haryana Government Gazette).
  • CAQM's revised GRAP schedule, approved on 28 September 2026, has 48 actions: 25 at Stage I, 8 at Stage II, 10 at Stage III and 5 at Stage IV (News On AIR, 29 September 2026).

Why is Delhi NCR a different data centre market?

Our India data centre market overview covers Mumbai, Chennai and the national picture. NCR differs in three ways.

First, almost all of it sits in one state. Noida and Greater Noida, both in Gautam Buddha Nagar district of Uttar Pradesh, held 86% of NCR's operational capacity and 96% of its development pipeline at Q4 2025 (W.Media, reporting Cushman & Wakefield, 11 March 2026). Gurugram has the offices and GCCs; most colocation capacity is across the Yamuna.

Second, Uttar Pradesh and Haryana now compete for the same projects, with new data centre policies issued six weeks apart in 2026.

Third, the Commission for Air Quality Management in NCR and Adjoining Areas (CAQM) runs the Graded Response Action Plan (GRAP), which covers diesel generator sets. Every server room here depends on DG backup, so this bites harder than in any other metro.

How much data centre capacity does Delhi NCR have?

Delhi NCR grew from 129 MW to 182 MW of operational capacity between Q4 2024 and Q4 2025, a 41% rise. Vacancy fell from 37% to 10.6% over the same year, and the pipeline dropped from 316 MW to 253 MW as projects went live (W.Media, 11 March 2026).

Bar chart of Delhi NCR operational data centre capacity: 129 MW in Q4 2024, 146 MW in H1 2025, 182 MW in Q4 2025 and 183 MW in H1 2026, with Noida and Greater Noida holding 86%
Delhi NCR operational data centre capacity. Source: Cushman & Wakefield (via Real Estate Asia and W.Media; H1 2026 update, 23 Sep 2026).
Period Operational capacity What else the report said
Q4 2024 129 MW Base year
H1 2025 146 MW Vacancy hit 44%; Noida and Greater Noida had 92% of a 233 MW pipeline
Q4 2025 182 MW Vacancy 10.6%; about 12% of India's operational capacity
H1 2026 183 MW 387 MW of future supply

Sources: Cushman & Wakefield, via Real Estate Asia (H1 2025), W.Media (Q4 2025) and the C&W India Data Centre H1 2026 update (23 September 2026).

For a buyer, the 2025 vacancy cushion has gone. Almost half the stock was empty in H1 2025; by year end, about one rack in ten. If you need racks in Noida in 2027, start talking to providers now.

What does the UP Data Centre Policy 2026 offer?

UP has raised its ambition twice. The original 2021 policy targeted 250 MW and ₹20,000 crore (UP Data Centre Policy 2021). The First Amendment of 2022 raised that to 900 MW, ₹30,000 crore and at least 8 private data centre parks (UP Data Centre Policy 2021, First Amendment 2022).

The UP Data Centre Policy 2026 was notified by G.O. No. 536/78-2-2026 dated 9 July 2026 and runs for five years. It aims for 2 GW+ of additional capacity, over ₹2 lakh crore of investment and at least 50% renewable energy in new data centres by 2030 (UP Data Centre Policy 2026).

Delivery has lagged the targets. UP Electronics Corporation (UPLC), the nodal agency, lists 644 MW of proposed capacity and ₹21,342.90 crore of proposed investment as on June 2025. Of that, 133 MW from 7 of 8 listed projects was commercialised, from NIDP (Hiranandani), NTT, Adani, ST Telemedia, SKVR Software and Web Werks (UPLC data centre policy page).

Bar chart of Uttar Pradesh data centre targets and results: 250 MW 2021 target, 900 MW 2022 target, 644 MW proposed, 133 MW commercialised, 2,000 MW additional target in the 2026 policy
Uttar Pradesh data centre targets versus results. Sources: UP Data Centre Policy 2021, First Amendment 2022 and Policy 2026; UPLC policy page.

The main incentives in the 2026 policy:

Incentive Data centre park (40 MW+) Data centre unit (2 to 40 MW)
Core subsidy 60% of term loan interest for 7 years, up to ₹10 crore a year and ₹50 crore in total 7% capital subsidy on eligible fixed capital investment, up to ₹20 crore, paid over 10 years
Land (from state agencies) 25% subsidy in Paschimanchal (includes Gautam Buddha Nagar and Ghaziabad); 50% in Bundelkhand and Purvanchal Same
Stamp duty 100% exemption on the first transaction Same
Wheeling and transmission 50% off for 25 years on intrastate power; 75% off for renewable power Same
Electricity duty Not listed 100% exemption for 10 years
Certification 25% of Tier III and 50% of Tier IV certification cost reimbursed Same
Green booster Higher subsidy caps for PUE of 1.35 or less and renewable share above 70% Same, at lower amounts

The policy also treats data centres as an essential service under ESMA. It keeps DG set space out of FAR and allows multi-level DG stacking with a fire NOC. Edge data centres (at least 10 sites of 50 kW or more, 2 MW in total) get 25% of their bandwidth bills back, up to ₹2.5 lakh a year per site for three years.

Note that captive data centres are excluded. Your own Noida server room gets none of this; the incentives go to colocation and cloud providers.

What does Haryana's Data Centre Policy 2026 offer?

Haryana notified its policy through Notification No. 20/12/2026-4IB-1, published in the Haryana Government Gazette (Extraordinary) on 27 May 2026. It runs five years and targets ₹10,000 crore of investment (Haryana Data Centre Policy 2026, Gazette).

Haryana sorts data centres by contracted power. A hyperscale site is above 10 MW, a core site 1 to 10 MW, and an edge site 300 kW to 1 MW. Units need at least 1 MW and parks at least 20 MW to qualify. Captive data centres are excluded here too.

  • Capex support. 20% of eligible capex for hyperscale, capped at ₹25 crore per unit. 10% for core, capped at ₹1 crore per MW. Paid in 10 annual instalments.
  • Opex support for 5 years. 50% of eligible opex for hyperscale, up to ₹8 crore a year, and 30% for core, up to ₹4 crore a year. Eligible opex includes net SGST, electricity duty and wheeling charges for power bought from outside the state.
  • Parks. 20% of eligible capex, capped at ₹15 crore.
  • Building rules. The Haryana Building Code allows FAR of 500%, 60% ground coverage and no maximum height for data centres. Data centres were declared a separate infrastructure industry by notification dated 22 November 2023.
  • Power and fibre. The state says it will try to provide dual grid supply and redundant last-mile connectivity.

UP's offer is wider on power. Haryana's is simpler: cash back on capex and opex. For a colocation buyer, it means more choice on both sides of Delhi.

How do GRAP rules affect DG sets at NCR data centres and server rooms?

GRAP is CAQM's set of actions that tighten in four stages as Delhi's air gets worse. Our post on dust monitoring and GRAP rules explains the stages.

CAQM approved a revised GRAP schedule on 28 September 2026, with 48 actions: 25 at Stage I, 8 at Stage II, 10 at Stage III and 5 at Stage IV (News On AIR, 29 September 2026). The change that matters most for IT teams: media reports say DG set actions moved from Stage II to Stage I, so they would apply from the first stage of the winter. We couldn't open CAQM's official schedule to confirm this, so check the current CAQM order before you plan around it (CareerIndia, 1 October 2026).

The capacity rules come from CAQM's 2024 revision of the schedule:

DG capacity What CAQM asks for Use during GRAP
19 kW (23 kVA) to under 62 kW (73 kVA) Dual fuel mode No restriction
62 kW (73 kVA) to under 800 kW (1,000 kVA) Dual fuel mode, or a retrofitted emission control device from a certified agency No restriction
Any set not on dual fuel only because gas isn't available Only for prescribed emergency services

Source: Lexplosion summary of the CAQM revised GRAP schedule, 28 September 2024.

Earlier versions of GRAP listed "telecommunication/data services" among the emergent and essential services that could keep running DG sets (Shardul Amarchand Mangaldas on Mondaq, 31 August 2022). Don't rely on an exemption. Lists change, and an inspector may not see your office server room as a "data service". Make the DG set compliant instead, with dual fuel or a certified emission control device, and keep stack tests on file. For sets of 800 kW and above, read the current CAQM direction.

Also size your UPS and batteries so short grid cuts never start the DG; our UPS sizing guide for server rooms covers runtime maths. If you colocate, ask for the provider's DG compliance papers.

What are the power options for data centres in Noida and Gurugram?

In UP, the 2026 policy promises 24x7 supply to data centre parks and units that arrange two dedicated feeders. Units outside parks may buy power through open access, with cross subsidy surcharge set by the Uttar Pradesh Electricity Regulatory Commission (UPERC). Parks can apply for a distribution licence, and units can seek deemed franchisee status for sub-metering (UP Data Centre Policy 2026).

For green power, the central Green Energy Open Access Rules, notified on 6 June 2022, cut the open access threshold for renewable power from 1 MW to 100 kW and set a 15-day approval window (Renewable Watch, 7 June 2022). That brings a mid-size facility within reach. Haryana's charges are set by the Haryana Electricity Regulatory Commission (HERC), so check the current HERC order before you model savings.

Ask any site how many independent feeders it has, what share of power is contracted renewable, and its measured PUE. UP's green booster rewards PUE of 1.35 or less, a useful benchmark.

Colocation or on-premise: what should an NCR enterprise choose?

The general trade-offs are in our data centre design guide on tiers and redundancy. NCR adds local factors:

NCR factor On-premise server room Noida or Gurugram colocation
DG compliance under GRAP Your job: retrofit, gas supply, tests Provider's job; check their papers
Power Usually one feeder in an office or plant Ask how many independent feeders the site has
Policy benefits None (captive sites excluded in UP and Haryana) Providers get them, which can show up in pricing
Latency to Delhi, Gurugram and Noida users Best for plant systems Good across NCR
Disaster recovery Needs a second site anyway Still needs a site outside NCR

A common NCR pattern: plant and latency-sensitive systems on site, core systems in a Noida or Gurugram colocation cage, and disaster recovery in Mumbai or Chennai.

How do you evaluate a data center company in India for an NCR project?

We don't rank providers. Ask every shortlisted data center company in India the same questions and compare the answers in writing:

  1. Location and state. Is the site in UP or Haryana, and has it got a Letter of Comfort or approval under the state policy?
  2. Power. How many independent feeders, from which substations? What's the contracted load headroom for your racks?
  3. DG and GRAP. Are all DG sets on dual fuel or fitted with certified emission control devices? Can you see the latest stack test reports and any CAQM or pollution board notices?
  4. UPS and batteries. What topology, what runtime at full load, and when were batteries last replaced?
  5. Certification. Tier III or IV, by whom, for design or the built facility?
  6. Density. What kW per rack can they support today, and is liquid cooling possible later?
  7. Carriers. How many carriers are in the building, and is there a cloud on-ramp?
  8. Green power and PUE. What share is renewable under contract, and what was last year's measured PUE?
  9. Water. Which cooling system do they run, how much water does it use, and is there treated water reuse?
  10. Exit terms. Notice period, migration support and data destruction certificates.

Asset Online Pvt Ltd (AOPL) designs and supports data centre infrastructure for enterprises across India, from server rooms to colocation migrations.

FAQs

Where are most data centres in Delhi NCR? In Noida and Greater Noida, with 86% of NCR's operational capacity at Q4 2025 (Cushman & Wakefield).

What is the UP Data Centre Policy 2026 target? 2 GW+ of additional capacity and over ₹2 lakh crore of investment over five years from 9 July 2026.

Does Haryana have a data centre policy? Yes. Notified on 27 May 2026, it targets ₹10,000 crore and reimburses capex and opex for data centres of 1 MW and above.

Can I run a diesel generator for my server room during GRAP? Sets from 19 kW to under 800 kW can run if they meet CAQM's dual fuel or emission control requirements. Reports say the September 2026 revision moved DG actions to Stage I, so get compliant before winter.

Do state data centre incentives apply to an in-house server room? No. Both the UP and Haryana policies exclude captive data centres. The benefits go to colocation and cloud providers.

Planning a move to a Noida or Gurugram colocation site, or fixing power and DG compliance at your own server room? Talk to AOPL.