Short answer: IT infrastructure for a new office means the structured cabling, Wi-Fi, network racks, switches, UPS power, firewall and logging that must be in place before staff move in. Plan it alongside the interior fit-out, not after. Size ports, access points, rack space and UPS from headcount and floor area, start the internet order early, and build CERT-In and DPDP logging into the design. A good IT infrastructure company will do this as one documented, tested project.

Free Excel tool Office IT Fit-Out Checklist and Budget Planner comes free with this guide. Download now ↓

This guide covers why fit-outs are rising, what to plan in each layer, the Indian rules that apply from day one, a realistic timeline, cost benchmarks, how to pick an IT infrastructure company, and a free Excel checklist and budget planner.

  • Office leasing in India's top seven cities hit a record 83.3 million sq ft in 2025, up 8% from 77.2 million sq ft in 2024 (JLL, reported by Outlook Business, January 2026).
  • Cushman & Wakefield's 2026 guide puts the average office fit-out cost at ₹5,847 to ₹6,567 per sq ft across eight Indian cities, with Mumbai the highest.
  • CERT-In's directions of 28 April 2022 require logs of all ICT systems to be kept for a rolling 180 days in India, clocks synced to NIC or NPL time, and incidents reported within 6 hours.
  • Under the DPDP Rules 2025, reasonable security safeguards and breach reporting apply from 14 May 2027, and the Act's highest penalty, up to ₹250 crore, is for failing to keep those safeguards (PIB and Shardul Amarchand Mangaldas, November 2025).

Why are so many Indian offices being fitted out now?

Because companies are leasing more space than ever. JLL counted 83.3 million sq ft of gross office leasing across seven cities in 2025, up 8% on 2024. Global firms took 58% of it (Outlook Business, 27 January 2026). Colliers, which tracks only Grade A space, put 2025 at 71.5 million sq ft, up 6% (RealtynMore, 25 December 2025).

2026 is running ahead. Colliers reported 54.4 million sq ft of Grade A leasing from January to September 2026, up 7% year on year. Bengaluru took 15.7 million sq ft and Hyderabad 9.4 million sq ft, up 47%. Colliers expects 75 to 80 million sq ft for the full year (Construction World, 29 September 2026).

Bar chart of India office leasing: JLL 77.2 million sq ft in 2024 and 83.3 million in 2025; Colliers 71.5 million Grade A in 2025 and 54.4 million in January to September 2026
India office leasing by tracker. Sources: JLL via Outlook Business (27 Jan 2026); Colliers India via RealtynMore (25 Dec 2025) and Construction World (29 Sep 2026).

Every lease becomes a fit-out, and every fit-out needs IT. Trackers count different cities, so treat the figures as a range.

What does IT infrastructure for a new office include?

Layer What it covers Reference to ask for
Passive cabling Copper to every desk, fibre between racks, patch panels, labels TIA-568 / ISO/IEC 11801, test reports
Telecom room and racks Rack space, cable managers, cooling, earthing, access NBC 2016 Part 8 Sections 2 and 6
Active network Access and core switches, PoE budget, firewall, router IEEE 802.3bt for PoE
Wi-Fi Access points, controller or cloud management, guest network IEEE 802.11ax / 802.11be
Power Dedicated circuits, UPS, generator changeover NBC 2016 Part 8 Section 2
Security and logging NTP, log storage, firewall policy, access control, CCTV CERT-In directions 2022, DPDP Rules 2025
Connectivity Two ISPs on separate paths, ideally ISP SLA

The National Building Code 2016 has a full section on this. Part 8 (Building Services) includes Section 2, Electrical and Allied Installations, and Section 6, Information and Communication Enabled Installations (BIS, National Building Code). BIS describes the NBC as a model code, so check what your state and building owner have adopted.

How should you plan structured cabling for a new office?

Structured cabling is a standards-based system of cables, outlets, patch panels and racks that any device can plug into. The two main standards are TIA-568 and ISO/IEC 11801.

Three rules drive most of the design:

  1. Distance. The fixed cable from rack to outlet (the permanent link) can be up to 90 m. The full channel, including patch cords, is capped at 100 m (Fluke Networks).
  2. Test the permanent link on a new install, and get a certified test report for every port.
  3. Plan for PoE and Wi-Fi 7. Access points, cameras and phones are now powered over the same cable. That is why many new offices now specify Cat 6A.

Get the cabling in before ceilings and partitions close. Rework later costs far more. Our guide to structured cabling and network racks covers Cat 6 versus Cat 6A, labelling and the common mistakes.

How many Wi-Fi access points does an office need?

Size for capacity first, then check coverage. An open-plan floor full of laptops and video calls runs out of airtime well before it runs out of signal.

Pick the standard with an eye on the lease term. IEEE 802.11ax (Wi-Fi 6) was published in May 2021 (IEEE). IEEE 802.11be (Wi-Fi 7) was approved in September 2024 and published in July 2025, with at least one mode reaching 30 Gbit/s (IEEE).

India opened the lower 6 GHz band in January 2026. The government notification of 20 January 2026 made 5925 to 6425 MHz licence-exempt for low-power indoor use, with channels up to 320 MHz (Broadband India Forum, 22 January 2026). That's the band Wi-Fi 6E and Wi-Fi 7 use. For a new office signing a 5 to 9 year lease, tri-band Wi-Fi 7 access points are worth pricing.

Practical steps:

  • Count users and devices per zone, not just square feet.
  • Do a predictive survey on the final layout, then a post-install validation survey.
  • Check the PoE class each access point needs. Under IEEE 802.3bt, Type 3 gives up to 60 W at the switch (51 W at the device), and Type 4 up to 90 W (71 W at the device) (Ethernet Alliance).

Our posts on enterprise Wi-Fi 6, 6E and 7 and network switches and PoE go deeper.

How much rack space, power and UPS do you need?

Work it out from the port count.

  • Rack space. One 24-port patch panel, one horizontal cable manager and one 48-port switch each take 1U. Add the firewall, router, UPS and any servers. Then add a growth allowance (the planner uses 40% as an example).
  • Load. Add the switch base load, the PoE load (access points, cameras, phones) and anything else in the rack.
  • UPS. kVA = kW ÷ the UPS output power factor. Leave headroom: the planner assumes no more than 75% load, as an example. Size the runtime to cover generator changeover.
  • Electrical. Ask for a dedicated, earthed circuit for each rack, and confirm the cooling for the room. A converted store room without either is a common problem.

Our guide to UPS for server rooms covers topologies and batteries. The free Excel planner below does this arithmetic for you.

Which Indian rules affect a new office network from day one?

Two sets of rules shape the network design, even for a small office.

CERT-In directions, 28 April 2022. These directions under section 70B(6) of the IT Act apply to service providers, intermediaries, data centres, body corporates and government bodies (CERT-In, No. 20(3)/2022-CERT-In). For a new office they mean:

  • Sync all ICT system clocks to NIC or NPL NTP servers, or to sources traceable to them.
  • Report listed cyber incidents to CERT-In within 6 hours of noticing them.
  • Enable logs of all ICT systems and keep them securely for a rolling 180 days, within India.
  • Name a point of contact for CERT-In.

So the firewall, switches, Wi-Fi controller and servers all need NTP and log forwarding set up at commissioning. Budget for log storage that covers 180 days.

DPDP Act 2023 and DPDP Rules 2025. The government notified the Rules on 14 November 2025, with an 18-month phased start (PIB backgrounder, 17 November 2025). Notice and consent, breach reporting and reasonable security safeguards apply from 14 May 2027. The Rules also ask data fiduciaries to keep personal data, traffic data and processing logs for at least one year (Shardul Amarchand Mangaldas). An office fitted out today will still be in use when these start. Plan the log storage and access control for it now.

This is a summary of what the rules say, not legal advice. Our post on CERT-In rules and the DPDP Act has more.

What does an office IT fit-out timeline look like?

IT starts before the civil work and finishes after it. A typical sequence:

Phase Typical timing IT tasks
Lease and design Before signing Check risers, power, telecom room space, ISP presence, existing cable records
Detailed design 12 to 16 weeks before move-in Port and AP count, rack layout, UPS sizing, BOQ, tender
Order long-lead items 10 to 12 weeks before ISP lines, switches, access points, UPS
First fix During civil work Containment, cable pulling before ceilings close
Second fix 4 to 6 weeks before Terminate, test, rack and dress, mount APs
Commissioning 2 to 3 weeks before Configure switches, Wi-Fi, firewall, NTP, logging; Wi-Fi survey
Testing and handover Last week User tests, as-built drawings, test reports, passwords handed over

The weeks above are a planning example, not a rule. Telecom lines alone can take 4 to 6 weeks, and systems should be tested 48 to 72 hours before staff arrive (Brigade Group, July 2026).

What does an office fit-out cost in India?

Cushman & Wakefield's 2026 guide gives average fit-out costs for a collaborative hybrid workplace. Mumbai is highest at ₹6,567 per sq ft, then Delhi at ₹6,207 and Bengaluru at ₹6,027. Ahmedabad, Chennai, Hyderabad, Kolkata and Pune sit at ₹5,847 (Cushman & Wakefield, India Office Fit Out Costs 2026).

Bar chart of 2026 office fit-out cost per sq ft: Mumbai ₹6,567, Delhi ₹6,207, Bengaluru ₹6,027, and ₹5,847 in Ahmedabad, Chennai, Hyderabad, Kolkata and Pune
Average office fit-out cost by city, whole fit-out. Source: Cushman & Wakefield, India Office Fit Out Costs and Market Insights 2026.

That's the whole fit-out, not just IT. The guide's public page doesn't break out the IT share, so don't take a percentage from it. Build the IT budget bottom up from your own quotes:

Cost line What drives it
Cabling Number of drops, Cat 6A or Cat 6, fibre backbone, testing
Racks and containment Racks, cable managers, trays, earthing
Switching Port count, PoE budget, stacking, uplinks
Wi-Fi AP count, Wi-Fi 6 or 7, licences
Firewall and security Throughput, licences, log storage for 180 days
UPS and power kVA, runtime, battery type, electrical work
Services Design, survey, installation, commissioning, AMC

A worked example: a 10,000 sq ft office in Pune at ₹5,847 per sq ft is about ₹5.8 crore for the full fit-out at the benchmark. Your IT line sits inside that. The planner shows your IT total as a share of the benchmark so you can sanity-check it.

Free download: Office IT Fit-Out Checklist and Budget Planner (Excel)

Preview of the free office IT fit-out checklist and budget planner in Excel
Free Excel tool
Office IT Fit-Out Checklist and Budget Planner
Enter headcount, floor area, desks and devices. The sheet works out cable drops, switch ports, PoE budget, access points, rack U and UPS kVA, tracks 30 fit-out tasks by phase, and totals your budget against a city fit-out benchmark.
  • Sizing for drops, APs, racks, PoE and UPS kVA
  • 30-task phased checklist with owner, status and dates
  • Budget with your unit prices and a city cost benchmark
Download the free Excel file ↓
Excel (.xlsx) · Example values filled in · No sign-up

Enter headcount, floor area, desks, meeting rooms and devices. The sizing sheet works out cable drops, patch panels, switch ports, PoE budget, access points, rack U and UPS kVA. The checklist sheet has 30 tasks in seven phases with owner, status and dates. The budget sheet takes your own unit prices and compares the IT total with the Cushman & Wakefield benchmark for your city. Yellow cells are inputs. Every example value is marked as an example.

How do you choose an IT infrastructure company for an office fit-out?

An IT infrastructure company designs, supplies, installs and supports the cabling, network, Wi-Fi, power and security in one scope. One accountable partner beats five separate vendors pointing at each other. Ask these questions:

  1. Will you do a site survey and a predictive Wi-Fi design before quoting?
  2. Which cabling standard will you design to, and will we get a certified test report for every port?
  3. Who is the cabling manufacturer, and is there a system warranty?
  4. How did you work out the PoE budget and UPS size? Show the arithmetic.
  5. Will you set up NTP and log forwarding to meet the CERT-In 180-day rule?
  6. What do we get at handover: as-built drawings, port maps, configs, passwords?
  7. Who coordinates with the interior contractor and the ISP?
  8. What does the AMC cover, and what are the response times?
  9. Can you show a similar office you have fitted out, with a reference we can call?

See how to choose a system integrator and IT infrastructure services and AMC costs in India for more on scope and contracts.

FAQs

When should IT planning start for a new office? Before you sign the lease. Check risers, power, telecom room space and which ISPs reach the building. Detailed design usually starts 12 to 16 weeks before move-in.

Is Cat 6 enough, or do we need Cat 6A? Cat 6 works for most desks today. Cat 6A is the safer choice for access points and high-power PoE, and for a lease of five years or more.

Do CERT-In rules apply to a small private office? The directions cover body corporates, so most companies are included. The 180-day log rule and NTP sync affect how you set up the firewall and switches.

How many access points do we need? It depends on users, devices and layout. Size by users per AP first, then check coverage with a survey. The free planner gives a starting estimate.

Planning a new office? See Asset Online Pvt Ltd (AOPL) IT infrastructure services, enterprise networking and network security, or contact us.

Sources

  • CERT-In, Directions under section 70B(6) of the IT Act, No. 20(3)/2022-CERT-In, 28 April 2022: PDF
  • Press Information Bureau, DPDP Rules 2025 Notified, 17 November 2025: PDF
  • Shardul Amarchand Mangaldas, Enforcement of the DPDP Act and notification of the DPDP Rules: AMS
  • Bureau of Indian Standards, National Building Code of India 2016: BIS
  • IEEE 802.11ax-2021: IEEE; IEEE 802.11be-2024: IEEE; IEEE 802.3bt-2018: IEEE
  • Ethernet Alliance, Introducing IEEE P802.3bt Power over Ethernet, June 2018: PDF
  • Fluke Networks, Channel, permanent link, patch cords, MPTL, 2019: Fluke Networks
  • Broadband India Forum, press release on delicensing the lower 6 GHz band, 22 January 2026: PDF
  • Outlook Business, JLL data on 2025 office leasing, 27 January 2026: Outlook Business
  • RealtynMore, Colliers India 2025 office leasing, 25 December 2025: RealtynMore
  • Construction World, Colliers India office leasing January to September 2026, 29 September 2026: Construction World
  • Cushman & Wakefield, India Office Fit Out Costs and Market Insights 2026: Cushman & Wakefield
  • Brigade Group, Office relocation checklist, 27 July 2026: Brigade