Digital Twin for Manufacturing: What It Really Takes

hero background
AI and RoboticsIndustry 4.0

Digital Twin for Manufacturing: What It Really Takes

Back to all blogs

Short answer: a digital twin is a virtual model of a machine, line or plant that is kept up to date with live data from the real thing, and that feeds decisions back to it. That two-way loop is what separates a twin from a 3D model or a dashboard. Most Indian manufacturers are still at pilot stage: in a 2024 Dassault Systèmes and Nasscom survey, 70% of Indian enterprises were in proof-of-concept or pilot. Start with one asset, one decision and clean data.

This guide explains what a digital twin really is, the maturity levels, the standards, what data it needs, realistic first projects and what to ask a vendor.

What is a digital twin?

Definitions vary, which is part of the problem. Three authoritative ones:

  • NIST describes a digital twin as an electronic representation of a real-world physical or non-physical entity, such as a building, a machine or a process. Its February 2025 report looks at the components, functions, cybersecurity and trust issues of digital twins (NIST IR 8356, 14 February 2025).
  • The US National Academies (2024) stress two elements: modelling and simulation of the physical counterpart, and a bidirectional interaction, where data updates the model and the model informs decisions about the physical system (National Academies, Foundational Research Gaps and Future Directions for Digital Twins, 2024).
  • ISO 23247 gives a digital twin framework specifically for manufacturing. Part 2 (October 2021) sets out a reference architecture with domains for the observable manufacturing elements, device communication, the digital twin itself and its users (ISO 23247-2:2021, via Standards Council of Canada).

The common thread: a twin is connected to the real asset, updated as conditions change, and used to make decisions.

Digital model, digital shadow or digital twin?

A widely cited classification by Kritzinger and colleagues (2018) separates three levels by how data flows. As a 2024 University of Antwerp report summarises it: with no automated data flow between the physical and digital, it's a digital model; when data flows automatically from the physical to the digital, it's a digital shadow; only when flows in both directions are automated is it a digital twin (Paredis, Vangheluwe and Ramos Albertins, "To Twin Or Not To Twin", University of Antwerp, 2024).

Level Physical to digital Digital to physical Typical example
Digital model Manual Manual CAD model, offline simulation of a line
Digital shadow Automatic Manual Live dashboard of a machine with a model behind it
Digital twin Automatic Automatic Model adjusts setpoints or schedules on the real line
Diagram of three levels: digital model with both data flows manual, digital shadow with automatic physical to digital flow, digital twin with both flows automatic
Kritzinger et al. (2018), as summarised by the University of Antwerp (2024).

Most "digital twin" projects in Indian plants today are digital shadows. That's fine. A good shadow is a sensible first step, as long as everyone knows what they've bought.

Where are Indian manufacturers on adoption?

A June 2024 report by Dassault Systèmes and Nasscom, covering 130 large and mid-sized companies in India, Europe and Asia-Pacific, found for India (Outlook Business, 17 June 2024):

  • 70% of Indian enterprises are still at proof-of-concept or pilot stage.
  • 80% spend less than 7% of their technology budget on virtual twins, and 25% have no formal budget for them.
  • Twins are mostly used at product level (40%) and process level (23%).
  • 75% say choosing the right supplier is a major challenge.
  • Fewer than 20% have implemented advanced process automation.
Bar chart of Indian enterprises in a 2024 survey: 80% spend under 7% of tech budget on twins, 75% cite supplier selection as a challenge, 70% at proof-of-concept or pilot, 25% have no formal twin budget
Dassault Systèmes and Nasscom report, via Outlook Business, 17 June 2024.

Practitioners elsewhere report the same confusion. A NIST and Chalmers University study of discrete manufacturers found that the many different definitions of a digital twin had made adoption difficult and slow, especially for smaller firms (Bärring, Johansson and Shao, ASME IMECE 2020).

What does a manufacturing digital twin need?

Layer What it means in a plant Common gaps
Asset and process model Physics, rules or machine-learning model of the asset Model too detailed or not validated
Sensors and machine data PLC tags, energy meters, vibration, temperature, counts Old machines without data ports
Connectivity OPC UA, MQTT, edge gateways Patchy OT networks
Context data MES, ERP, maintenance records, quality data Data in spreadsheets and paper
Data platform Time-series store, historian, data lake No common naming or tagging
Decision loop Who or what acts on the twin's output No owner for the decision
Security Access control, segmentation, trust in data Twin opens a path into OT

The National Academies report makes two points worth putting in any project charter. First, a twin should be fit for purpose: its fidelity should match the decision it supports, not aim for the most detailed model possible. Second, verification, validation and uncertainty checks aren't a one-time step; they have to continue as the plant and the model change. It also warns that aspirational claims run ahead of current evidence.

NIST's report adds the security angle. A twin is connected to real equipment, so it's part of your attack surface. See our guide to edge computing for Indian factories for how to keep OT data paths segmented.

What are realistic first digital twin projects?

Pick one asset, one decision and one measurable outcome.

First project Decision it supports Data needed Measure
Critical machine health shadow When to service a compressor, pump or spindle Vibration, temperature, current, run hours Unplanned downtime
Line throughput model Where the bottleneck is, what buffer sizes to use Cycle times, stoppages, counts Output per shift
Energy twin of a utility system Which compressor, chiller or boiler to run, at what load Energy meters, pressures, flows kWh per unit produced
Layout and material flow simulation Where to put a new machine or AGV route Layout, routings, volumes Travel distance, WIP
Process recipe model Setpoints for a furnace, dryer or moulding machine Process parameters and quality results Scrap rate

The first project in the table often overlaps with predictive maintenance. Read our predictive maintenance guide for the sensor and ROI side. For layout and AGV flow, see our AGV guide.

How do you build the business case?

Use the decision, not the technology, as the unit of value:

  1. Name the decision the twin will improve (for example, compressor sequencing).
  2. Measure today's baseline for at least a month (kWh per unit, downtime hours, scrap rate).
  3. Estimate the improvement from a pilot, not a brochure.
  4. Count all costs: sensors and gateways, connectivity, data platform, modelling, software licences, integration, internal time, and ongoing model upkeep.
  5. Set a stop rule: if the pilot doesn't move the metric in an agreed period, stop or rescope.

The survey finding that 80% of Indian firms spend under 7% of tech budgets on twins isn't a problem in itself. A narrow, measured pilot doesn't need a large budget. Scaling without a proven pilot does.

What standards should you ask about?

  • ISO 23247 for the manufacturing digital twin framework and reference architecture.
  • OPC UA for machine data with context, and MQTT for lightweight messaging from edge devices.
  • IEC 62443 for securing industrial automation and control systems.
  • ISA-95 for linking shop floor data to MES and ERP.

Ask vendors how their architecture maps to ISO 23247's domains. If they can't explain where the data comes from, how the model is validated and who acts on its output, it's not ready.

Questions to ask a digital twin vendor

  • Is this a digital model, a digital shadow or a full digital twin? Which data flows are automated?
  • Which decision will this improve, and how will we measure it?
  • What data do you need from our machines, and what if older machines have no data port?
  • How is the model validated, and how will you keep it valid when we change the process?
  • Who owns the model, the data and the code if we change vendors?
  • Which standards does the platform support (OPC UA, MQTT, ISO 23247)?
  • How is the twin secured, and how does it connect to our OT network?
  • What will it cost to run each year after the pilot?

FAQs

What is a digital twin in manufacturing? A virtual model of a machine, line or plant that is updated automatically with live data and used to make decisions about the real asset.

What is the difference between a digital twin and a simulation? A simulation is usually run offline with assumed inputs. A digital twin is connected to the real asset, updates as conditions change, and informs decisions in both directions.

How many Indian companies use digital twins? In a 2024 Dassault Systèmes and Nasscom survey, 70% of Indian enterprises surveyed were still in proof-of-concept or pilot stage for relevant technologies.

What is ISO 23247? An ISO standard series that gives a digital twin framework for manufacturing. Part 2, published in 2021, sets out a reference architecture.

What is a good first digital twin project? A digital shadow of one critical machine or utility system, tied to one measurable decision such as maintenance timing or energy use.

Exploring a digital twin or a data-driven pilot for your plant? See our AI and robotics solutions, or talk to us. For the wider roadmap, read our Industry 4.0 roadmap for Indian manufacturers.